Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-161-13-43 04-207774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-5706 Federal Project: NONE Progress payment No. 19 Payment period ending: 06-01-10 TABER CONSTRUCTION INC P O BOX 1309 MARTINEZ CA 94553 Escrow No. 02408 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,411,075.78 0.00 2.a. Extra Work 481,757.23 0.00 b. Adjustment Comp. 40,070.41 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,932,903.42 0.00 5. Mobilization 6. Total Work Completed 3,932,903.42 7. Deductions 8. a.Contract Retentions -196,645.17 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 196,645.17 196,645.17 9. Total pay to Contractor 3,932,903.42 196,645.17 10. Reduction Amt to Escrow -196,640.00 -196,640.00 11. Payment to Escrow 196,640.00 12. Net Pymt. this Estimate 5.17