Dept. of Trans. PROGRESS Serial No. Contract No. 09-164-09-11 04-219864 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 11% 04-SON-12-29.7/30.9 Federal Project: ACST-P012(101) P-P012(101) Progress payment No. 04 Payment period ending: 06-20-09 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 400,524.80 201,089.20 2.a. Extra Work 3,603.04 3,603.04 b. Adjustment Comp. 3. Materials on Hand 21,658.30 21,658.30 4. Earned Subject to Retention 425,786.14 226,350.54 5. Mobilization 123,500.00 58,500.00 6. Total Work Completed 527,627.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 549,286.14 284,850.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 284,850.54