Dept. of Trans. PROGRESS Serial No. Contract No. 02-140-11-28 04-226124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 15% 04-MRN-101-8.4/9.7 Federal Project: ACNH-P101(992) CML-6204(42) Progress payment No. 04 Payment period ending: 05-20-02 DIABLO CONTRACTORS INC 7 CROW CANYON COURT, STE 100 SAN RAMON, CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 484,226.99 165,521.50 2.a. Extra Work 6,275.28 6,275.28 b. Adjustment Comp. 3. Materials on Hand 0.00 -3,570.00 4. Earned Subject to Retention 490,502.27 168,226.78 5. Mobilization 450,000.00 450,000.00 6. Total Work Completed 940,502.27 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -49,050.23 -16,822.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 881,452.04 591,404.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 591,404.10