Dept. of Trans. PROGRESS Serial No. Contract No. 04-079-14-22 04-226124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 04-MRN-101-8.4/9.7 Federal Project: ACNH-P101(992) CML-6204(42) Progress payment No. 26 Payment period ending: 03-20-04 DIABLO CONTRACTORS INC 7 CROW CANYON COURT, STE 100 SAN RAMON, CA 94583 Escrow No. 01963 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,286,801.68 13,200.00 2.a. Extra Work 1,255,330.31 1,851.00 b. Adjustment Comp. 382,627.00 12,419.45 3. Materials on Hand 4. Earned Subject to Retention 8,924,758.99 27,470.45 5. Mobilization 900,000.00 0.00 6. Total Work Completed 9,824,758.99 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -446,237.95 -1,373.52 b. Unsatisfactory Prog. -13,602.29 -1,373.52 c. Reduction after 95% Comp. 9. Total pay to Contractor 9,354,918.75 24,723.41 10. Reduction Amt to Escrow 11. Payment to Escrow 446,230.00 12. Net Pymt. this Estimate 24,723.41