Dept. of Trans. PROGRESS Serial No. Contract No. 05-050-11-29 04-226124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 04-MRN-101-8.4/9.7 Federal Project: ACNH-P101(992) CML-6204(42) Progress payment No. 30 Payment period ending: 02-20-05 DIABLO CONTRACTORS INC 7 CROW CANYON COURT, STE 100 SAN RAMON, CA 94583 Escrow No. 01963 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,312,097.68 25,296.00 2.a. Extra Work 1,413,586.93 -18,322.47 b. Adjustment Comp. 387,227.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,112,911.61 6,973.53 5. Mobilization 900,000.00 0.00 6. Total Work Completed 10,012,911.61 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -455,645.58 -348.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,547,266.03 6,624.85 10. Reduction Amt to Escrow 11. Payment to Escrow 455,640.00 12. Net Pymt. this Estimate 6,624.85