Dept. of Trans. PROGRESS Serial No. Contract No. 06-080-10-47 04-226134 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 99% 04-MRN-101-8.3/8.4 Federal Project: ACNH-Q101(57) Progress payment No. 25 Payment period ending: 03-20-06 BALFOUR BEATTY CONSTRUCTION INC 19435 WEST VALLEY HWY S-100 KENT, WA 98032 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,658,793.33 21,665.88 2.a. Extra Work 628,324.13 73,935.28 b. Adjustment Comp. 100,007.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,387,125.34 95,601.16 5. Mobilization 700,000.00 0.00 6. Total Work Completed 7,087,125.34 7. Deductions 8. a.Contract Retentions -319,356.27 -4,780.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,767,769.07 90,821.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,821.10