Dept. of Trans. PROGRESS Serial No. Contract No. 11-020-15-41 04-226144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-MRN-101-11.2/12.8 Federal Project: ACST-Q101(127) PE-Q101(127) CML-6204(43) Progress payment No. 42 Payment period ending: 01-20-11 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,751,736.03 -663.00 2.a. Extra Work 8,994,362.06 184,317.51 b. Adjustment Comp. 1,289,640.25 0.00 3. Materials on Hand 115,474.03 -9,464.00 4. Earned Subject to Retention 50,151,212.37 174,190.51 5. Mobilization 4,385,000.00 0.00 6. Total Work Completed 54,420,738.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 54,536,212.37 174,190.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,190.51