Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-07-39 04-228264 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 77% 04-CC-4-R14.6/23.0 Federal Project: NONE Progress payment No. 22 Payment period ending: 02-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,238,880.65 272,977.42 2.a. Extra Work 435,768.11 73,813.28 b. Adjustment Comp. 199,640.44 -5,270.88 3. Materials on Hand 4. Earned Subject to Retention 10,874,289.20 341,519.82 5. Mobilization 1,627,000.00 0.00 6. Total Work Completed 12,501,289.20 7. Deductions -3,434.59 0.00 8. a.Contract Retentions -543,714.46 -17,075.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,954,140.15 324,443.83 10. Reduction Amt to Escrow 11. Payment to Escrow 543,710.00 12. Net Pymt. this Estimate 324,443.83