Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-08-34 04-228264 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 96% 04-CC-4-R14.6/23.0 Federal Project: NONE Progress payment No. 27 Payment period ending: 06-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,022,034.65 1,217,607.34 2.a. Extra Work 555,910.62 85,926.01 b. Adjustment Comp. 196,782.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,774,728.25 1,303,533.35 5. Mobilization 1,627,000.00 0.00 6. Total Work Completed 15,401,728.25 7. Deductions -3,434.59 0.00 8. a.Contract Retentions -688,736.41 -65,176.66 b. Unsatisfactory Prog. 0.00 79,845.27 c. Reduction after 95% Comp. 9. Total pay to Contractor 14,709,557.25 1,318,201.96 10. Reduction Amt to Escrow 11. Payment to Escrow 688,730.00 12. Net Pymt. this Estimate 1,318,201.96