Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 02-213-13-25 04-228264 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-4-R14.6/23.0 Federal Project: NONE Progress payment No. 37 Payment period ending: 07-15-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,358,159.32 -256,965.00 2.a. Extra Work 867,578.72 2,086.46 b. Adjustment Comp. 885,682.55 -29,567.05 3. Materials on Hand 4. Earned Subject to Retention 15,111,420.59 -284,445.59 5. Mobilization 1,627,000.00 0.00 6. Total Work Completed 16,738,420.59 7. Deductions -51,434.59 -48,000.00 8. a.Contract Retentions -769,793.31 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 769,793.31 769,793.31 9. Total pay to Contractor 16,686,986.00 437,347.72 10. Reduction Amt to Escrow -769,770.00 -769,770.00 11. Payment to Escrow 769,770.00 12. Net Pymt. this Estimate -332,422.28