Dept. of Trans. PROGRESS Serial No. Contract No. Dept. of Trans. PROGRESS Serial No. Contract No. 05-237-10-05 07-4K9504 05-232-09-40 04-228444 PROGRESS PAYMENT VOUCHER %complete: %time: PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 100% Location: 64% 86% 07-LA-5-65.4/65.8 Federal Project: 04-CC-680-R0.0/R0.6 Federal Project: NONE 04-ALA-680-R21.5/R21.9 STPL-680 Progress payment No. 13 Payment period ending: 08-20-05 Progress payment No. 20 Payment period ending: 08-20-05 GRANITE CONSTRUCTION COMPANY BAY CITIES PAVING AND GRADING P.O. BOX 50085 INC WATSONVILLE, CA 95077 P O BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Escrow No. 00000 Total Estimate This Estimate Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,250.00 0.00 1. Contract Itms Without Mobil. 3,587,892.61 379,644.45 2.a. Extra Work 3,637,265.85 115,679.76 2.a. Extra Work 165,787.05 25,460.94 b. Adjustment Comp. 3. Materials on Hand b. Adjustment Comp. 4. Earned Subject to Retention 3,642,515.85 115,679.76 3. Materials on Hand 99,332.83 -8,689.62 4. Earned Subject to Retention 3,853,012.49 396,415.77 5. Mobilization 5. Mobilization 650,000.00 0.00 6. Total Work Completed 3,642,515.85 6. Total Work Completed 4,403,679.66 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,642,515.85 115,679.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,679.76 7. Deductions -83,999.10 0.00 8. a.Contract Retentions -192,650.62 -19,820.78 b. Unsatisfactory Prog. -88,098.67 -19,820.79 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,138,264.10 356,774.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 356,774.20