Dept. of Trans. 95% REDUCTION Serial No. Contract No. 06-354-07-56 04-228444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-CC-680-R0.0/R0.6 Federal Project: 04-ALA-680-R21.5/R21.9 STPL-680 Progress payment No. 37 Payment period ending: 12-20-06 BAY CITIES PAVING AND GRADING INC P O BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,185,451.88 6,981.80 2.a. Extra Work 553,453.08 5,314.30 b. Adjustment Comp. 219,953.52 24,656.72 3. Materials on Hand 4. Earned Subject to Retention 6,958,858.48 36,952.82 5. Mobilization 650,000.00 0.00 6. Total Work Completed 7,608,858.48 7. Deductions -178,871.04 0.00 8. a.Contract Retentions -347,942.92 -1,847.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 308,031.92 7,355.64 9. Total pay to Contractor 7,390,076.44 42,460.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,460.82