Dept. of Trans. FINAL Serial No. Contract No. 08-161-12-34 04-228554 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-680-2.9/4.3 Federal Project: 04-CC-680-6.7/7.6 STPL-6204(56) Progress payment No. 19 Payment period ending: 05-22-07 NEHEMIAH CONSTRUCTION INC 4790 E 2ND STREET BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,837,352.55 0.00 2.a. Extra Work 1,232,702.80 -61,840.00 b. Adjustment Comp. 748,760.85 414,000.00 3. Materials on Hand 4. Earned Subject to Retention 14,818,816.20 352,160.00 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 16,218,816.20 7. Deductions -5,558.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,213,258.20 352,160.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 352,160.00