Dept. of Trans. PROGRESS Serial No. Contract No. 04-022-18-51 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 46% 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 13 Payment period ending: 01-20-04 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,211,070.06 272,481.57 2.a. Extra Work 611,866.33 1,867.34 b. Adjustment Comp. 125,000.00 0.00 3. Materials on Hand 108,780.95 108,780.95 4. Earned Subject to Retention 10,056,717.34 383,129.86 5. Mobilization 2,755,000.00 0.00 6. Total Work Completed 12,702,936.39 7. Deductions -9,951.00 0.00 8. a.Contract Retentions -599,563.61 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,202,202.73 383,129.86 10. Reduction Amt to Escrow 11. Payment to Escrow 599,560.00 12. Net Pymt. this Estimate 383,129.86