Dept. of Trans. PROGRESS Serial No. Contract No. 04-079-15-56 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 54% 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 15 Payment period ending: 03-20-04 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,985,408.82 980,431.01 2.a. Extra Work 915,278.40 151,837.72 b. Adjustment Comp. 152,345.00 27,345.00 3. Materials on Hand 128,309.55 -9,569.30 4. Earned Subject to Retention 12,181,341.77 1,150,044.43 5. Mobilization 2,755,000.00 0.00 6. Total Work Completed 14,808,032.22 7. Deductions -9,951.00 0.00 8. a.Contract Retentions -609,067.09 -9,503.48 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,317,323.68 1,140,540.95 10. Reduction Amt to Escrow 11. Payment to Escrow 609,060.00 12. Net Pymt. this Estimate 1,140,540.95