Dept. of Trans. PROGRESS Serial No. Contract No. 04-300-14-46 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 22 Payment period ending: 10-20-04 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,915,802.48 1,556,389.26 2.a. Extra Work 1,628,921.67 38,256.71 b. Adjustment Comp. 196,699.80 -18,145.20 3. Materials on Hand 0.00 -10,500.00 4. Earned Subject to Retention 24,741,423.95 1,566,000.77 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 27,641,423.95 7. Deductions -170,271.00 -25,000.00 8. a.Contract Retentions -1,237,071.20 -78,300.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,234,081.75 1,462,700.73 10. Reduction Amt to Escrow 11. Payment to Escrow 1,237,070.00 12. Net Pymt. this Estimate 1,462,700.73