Dept. of Trans. PROGRESS Serial No. Contract No. 05-020-08-08 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 25 Payment period ending: 01-20-05 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,428,937.14 646,093.76 2.a. Extra Work 1,837,612.80 107,153.67 b. Adjustment Comp. 287,953.57 0.00 3. Materials on Hand 10,500.00 0.00 4. Earned Subject to Retention 27,565,003.51 753,247.43 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 30,454,503.51 7. Deductions -287,087.64 -55,765.59 8. a.Contract Retentions -1,378,250.18 -37,662.38 b. Unsatisfactory Prog. -37,662.36 -37,662.36 c. Reduction after 95% Comp. 9. Total pay to Contractor 28,762,003.33 622,157.10 10. Reduction Amt to Escrow 11. Payment to Escrow 1,378,250.00 12. Net Pymt. this Estimate 622,157.10