Dept. of Trans. PROGRESS Serial No. Contract No. 05-232-09-40 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 32 Payment period ending: 08-20-05 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,291,326.61 -450,539.94 2.a. Extra Work 3,082,204.04 243,658.07 b. Adjustment Comp. 1,060,964.67 233,396.13 3. Materials on Hand 4. Earned Subject to Retention 33,434,495.32 26,514.26 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 36,334,495.32 7. Deductions -865,271.00 0.00 8. a.Contract Retentions -1,671,724.77 -1,325.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,797,499.55 25,188.54 10. Reduction Amt to Escrow 11. Payment to Escrow 1,671,720.00 12. Net Pymt. this Estimate 25,188.54