Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-012-10-44 04-2285U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-680-15.6/24.3 Federal Project: ACNH-680-1(59) I-680-1(59) Progress payment No. 34 Payment period ending: 08-29-05 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 945512910 Escrow No. 02063 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,001,872.95 -12,530.18 2.a. Extra Work 4,472,411.54 1,338,053.83 b. Adjustment Comp. 1,017,893.93 -130,870.55 3. Materials on Hand 4. Earned Subject to Retention 34,492,178.42 1,194,653.10 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 37,392,178.42 7. Deductions -460,271.00 -405,000.00 8. a.Contract Retentions -1,671,724.77 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,671,724.77 0.00 9. Total pay to Contractor 36,931,907.42 789,653.10 10. Reduction Amt to Escrow -1,671,720.00 0.00 11. Payment to Escrow 1,671,720.00 12. Net Pymt. this Estimate 789,653.10