Dept. of Trans. PROGRESS Serial No. Contract No. Dept. of Trans. PROGRESS Serial No. Contract No. 05-201-14-24 04-2332U4 05-202-13-25 12-0126E4 PROGRESS PAYMENT VOUCHER %complete: %time: PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 64% Location: 12% 8% 12-ORA-5-41.5/43.5 Federal Project: 04-ALA-880-R0.0/2.9 Federal Project: STPL-6212(5) 04-SCL-880-8.2/10.5 ACNH-880-1(55) ER-6212(5) I-880-1(55) Progress payment No. 30 Payment period ending: 07-20-05 BELAIRE WEST LANDSCAPE INC Progress payment No. 04 Payment period ending: 07-20-05 P O BOX 6270 DESILVA GATES FCI A JOINT BUENA PARK CA 90622 VENTURE OF DESILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02036 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,546,685.00 3,125.00 2.a. Extra Work 248,440.24 2,249.00 b. Adjustment Comp. Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,408,704.81 1,403,570.64 3. Materials on Hand 2.a. Extra Work 27,469.94 27,469.94 b. Adjustment Comp. 4. Earned Subject to Retention 1,795,125.24 5,374.00 3. Materials on Hand 4. Earned Subject to Retention 4,436,174.75 1,431,040.58 5. Mobilization 15,000.00 0.00 5. Mobilization 2,950,000.00 0.00 6. Total Work Completed 1,810,125.24 6. Total Work Completed 7,386,174.75 7. Deductions 7. Deductions -10,885.60 -10,000.00 8. a.Contract Retentions 8. a.Contract Retentions -89,756.26 -268.70 b. Unsatisfactory Prog. b. Unsatisfactory Prog. c. Reduction after 95% Comp. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,375,289.15 1,421,040.58 9. Total pay to Contractor 1,720,368.98 5,105.30 10. Reduction Amt to Escrow 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 11. Payment to Escrow 89,480.00 12. Net Pymt. this Estimate 5,105.30 12. Net Pymt. this Estimate 1,421,040.58