Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-07-16 04-2332U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 23% 04-ALA-880-R0.0/2.9 Federal Project: 04-SCL-880-8.2/10.5 ACNH-880-1(55) I-880-1(55) Progress payment No. 15 Payment period ending: 06-20-06 DESILVA GATES FCI A JOINT VENTURE OF DESILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,234,383.00 1,339,601.96 2.a. Extra Work 355,129.40 89,320.65 b. Adjustment Comp. 1,672,367.37 0.00 3. Materials on Hand 1,149,088.89 54,679.14 4. Earned Subject to Retention 20,410,968.66 1,483,601.75 5. Mobilization 5,605,000.00 0.00 6. Total Work Completed 24,866,879.77 7. Deductions -21,364.47 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,994,604.19 1,483,601.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,483,601.75