Dept. of Trans. PROGRESS Serial No. Contract No. 07-139-07-35 04-2332U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 46% 04-ALA-880-R0.0/2.9 Federal Project: 04-SCL-880-8.2/10.5 ACNH-880-1(55) I-880-1(55) Progress payment No. 26 Payment period ending: 05-20-07 DESILVA GATES FCI A JOINT VENTURE OF DESILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,580,946.34 1,012,088.78 2.a. Extra Work 1,386,297.72 1,862.50 b. Adjustment Comp. 3,093,102.28 693,181.08 3. Materials on Hand 395,216.20 31,789.41 4. Earned Subject to Retention 35,455,562.54 1,738,921.77 5. Mobilization 5,900,000.00 0.00 6. Total Work Completed 40,960,346.34 7. Deductions -36,994.07 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,318,568.47 1,738,921.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,738,921.77