Dept. of Trans. PROGRESS Serial No. Contract No. 15-238-14-06 04-235624 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 8% Location: Federal Project: 04-SCL-101-52.0/52.6 CNHP-000C(366) 04-SM-101-0.0/0.6 Progress payment No. 003 Payment period ending: 08-20-15 GHILOTTI BROS/RM HARRIS JV 901 HOWE ROAD MARTINEZ, CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,110,803.44 360,361.19 2. a. Extra Work 40,836.83 40,692.51 b. Adustment Comp. 3. Materials on Hand 125,419.27 0.00 4. Earned Subject to Retention 1,277,059.54 401,053.70 5. Mobilization 750,000.00 0.00 6. Total Work Completed 1,901,640.27 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,027,059.54 401,053.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 401,053.70