Dept. of Trans. PROGRESS Serial No. Contract No. 16-203-09-20 04-235624 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 37% Location: Federal Project: 04-SCL-101-52.0/52.6 CNHP-000C(366) 04-SM-101-0.0/0.6 Progress payment No. 014 Payment period ending: 07-20-16 GHILOTTI BROS / RM HARRIS JV 901 HOWE RD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,264,226.42 432,568.96 2. a. Extra Work 503,523.43 61,399.68 b. Adustment Comp. 3. Materials on Hand 755,059.42 0.00 4. Earned Subject to Retention 5,522,809.27 493,968.64 5. Mobilization 1,425,000.00 0.00 6. Total Work Completed 6,192,749.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,947,809.27 493,968.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 493,968.64