Dept. of Trans. PROGRESS Serial No. Contract No. 18-204-10-12 04-235624 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 04-SCL-101-52.0/52.6 CNHP-000C(366) 04-SM-101-0.0/0.6 Progress payment No. 041 Payment period ending: 07-20-18 GHILOTTI BROS / RM HARRIS JV 901 HOWE RD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,133,523.14 121,500.85 2. a. Extra Work 1,504,563.54 0.00 b. Adustment Comp. 3. Materials on Hand 397,685.62 -5,129.00 4. Earned Subject to Retention 15,035,772.30 116,371.85 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 16,138,086.68 7. Deductions -17,100.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,518,672.30 116,371.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,371.85