Dept. of Trans. PROGRESS Serial No. Contract No. 18-023-10-38 04-235654 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 55% Location: Federal Project: 04-SM-101-1.6/2.2 NONE 04-SM-114-5.0/5.3 Progress payment No. 009 Payment period ending: 01-20-18 DISNEY/O C JONES JV 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,096,897.60 4,496,889.90 2. a. Extra Work 137,108.95 0.00 b. Adustment Comp. 3. Materials on Hand 752,334.68 561,002.15 4. Earned Subject to Retention 14,986,341.23 5,057,892.05 5. Mobilization 3,600,500.00 0.00 6. Total Work Completed 17,834,506.55 7. Deductions -14,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,572,841.23 5,057,892.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,057,892.05