Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-15-21 04-235654 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 57% Location: Federal Project: 04-SM-101-1.6/2.2 NONE 04-SM-114-5.0/5.3 Progress payment No. 011 Payment period ending: 03-20-18 DISNEY/O C JONES JV 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,540,211.83 966,595.99 2. a. Extra Work 174,015.00 11,295.99 b. Adustment Comp. 3. Materials on Hand 1,542,461.55 294,202.22 4. Earned Subject to Retention 18,256,688.38 1,272,094.20 5. Mobilization 3,600,500.00 0.00 6. Total Work Completed 20,314,726.83 7. Deductions -14,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,843,188.38 1,272,094.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,272,094.20