Dept. of Trans. PROGRESS Serial No. Contract No. 15-082-07-55 04-2356A4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 35% Location: Federal Project: 04-SM-101-0.9/3.6 NONE Progress payment No. 015 Payment period ending: 03-20-15 BORTOLUSSI & WATKIN INC 77 LARKSPUR STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,721.00 1,742.00 2. a. Extra Work 17,961.30 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 770,682.30 1,742.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 870,682.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 870,682.30 1,742.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,742.00