Dept. of Trans. PROGRESS Serial No. Contract No. 15-202-07-09 04-2356A4 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 44% Location: Federal Project: 04-SM-101-0.9/3.6 NONE Progress payment No. 019 Payment period ending: 07-20-15 BORTOLUSSI & WATKIN INC 77 LARKSPUR STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 762,225.00 1,876.00 2. a. Extra Work 28,546.73 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 790,771.73 1,876.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 890,771.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 890,771.73 1,876.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,876.00