Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-11-02 04-235724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 16% 04-SM-101-9.6/11.9 Federal Project: ACNH-P101(963) Progress payment No. 04 Payment period ending: 06-20-01 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 01709 Total Estimate This Estimate 1. Contract Itms Without Mobil. 514,460.76 138,087.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 514,460.76 138,087.80 5. Mobilization 395,000.00 0.00 6. Total Work Completed 909,460.76 7. Deductions 8. a.Contract Retentions -51,446.08 -13,808.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 858,014.68 124,279.02 10. Reduction Amt to Escrow 11. Payment to Escrow 51,440.00 12. Net Pymt. this Estimate 124,279.02