Dept. of Trans. PROGRESS Serial No. Contract No. 02-270-09-57 04-235724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SM-101-9.6/11.9 Federal Project: ACNH-P101(963) Progress payment No. 19 Payment period ending: 09-20-02 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 01709 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,103,565.13 36,324.00 2.a. Extra Work 744,663.55 214,513.33 b. Adjustment Comp. 20,652.35 -43,719.00 3. Materials on Hand 4. Earned Subject to Retention 7,868,881.03 207,118.33 5. Mobilization 790,000.00 0.00 6. Total Work Completed 8,658,881.03 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -393,444.05 -10,355.91 b. Unsatisfactory Prog. 0.00 11,332.95 c. Reduction after 95% Comp. 9. Total pay to Contractor 8,255,436.98 208,095.37 10. Reduction Amt to Escrow 11. Payment to Escrow 383,080.00 12. Net Pymt. this Estimate 208,095.37