Dept. of Trans. PROGRESS Serial No. Contract No. 08-110-07-28 04-235764 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 12% 04-SM-101-3.5/11.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 04-20-08 J J NGUYEN INC 3172 SALEM DR SAN JOSE CA 95127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,415.00 7,875.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 35,415.00 7,875.00 5. Mobilization 6. Total Work Completed 35,415.00 7. Deductions 8. a.Contract Retentions -2,609.60 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,805.40 7,875.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,875.00