Dept. of Trans. PROGRESS Serial No. Contract No. 04-170-15-18 04-2357A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 88% 04-SM-101-3.6/11.9 Federal Project: ACNH-Q101(18) Progress payment No. 16 Payment period ending: 06-20-04 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02065 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,601,906.19 2,245,850.31 2.a. Extra Work 293,926.54 30,426.39 b. Adjustment Comp. 1,230.00 0.00 3. Materials on Hand 337,302.86 -11,508.94 4. Earned Subject to Retention 16,234,365.59 2,264,767.76 5. Mobilization 2,275,000.00 0.00 6. Total Work Completed 18,172,062.73 7. Deductions -30,000.00 0.00 8. a.Contract Retentions -811,718.28 -113,238.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,667,647.31 2,151,529.37 10. Reduction Amt to Escrow 11. Payment to Escrow 811,710.00 12. Net Pymt. this Estimate 2,151,529.37