Dept. of Trans. PROGRESS Serial No. Contract No. 05-111-16-15 04-2357A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 99% 04-SM-101-3.6/11.9 Federal Project: ACNH-Q101(18) Progress payment No. 26 Payment period ending: 04-20-05 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02065 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,684,387.28 -161,570.23 2.a. Extra Work 2,156,651.05 196,410.39 b. Adjustment Comp. 183,624.42 145,921.42 3. Materials on Hand 0.00 -74,556.27 4. Earned Subject to Retention 23,024,662.75 106,205.31 5. Mobilization 2,275,000.00 0.00 6. Total Work Completed 25,299,662.75 7. Deductions -32,250.45 0.00 8. a.Contract Retentions -1,151,233.14 -5,310.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,116,179.16 100,895.04 10. Reduction Amt to Escrow 11. Payment to Escrow 910,000.00 12. Net Pymt. this Estimate 100,895.04