Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-195-08-52 04-2357A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-101-3.6/11.9 Federal Project: ACNH-Q101(18) Progress payment No. 40 Payment period ending: 07-11-06 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02065 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,842,386.29 0.00 2.a. Extra Work 2,645,556.99 36,676.00 b. Adjustment Comp. 261,465.80 0.00 3. Materials on Hand 0.00 -15,750.00 4. Earned Subject to Retention 23,749,409.08 20,926.00 5. Mobilization 2,275,000.00 0.00 6. Total Work Completed 26,024,409.08 7. Deductions -30,000.00 0.00 8. a.Contract Retentions -1,186,424.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,186,424.15 1,186,424.15 9. Total pay to Contractor 25,994,409.08 1,207,350.15 10. Reduction Amt to Escrow -910,000.00 -910,000.00 11. Payment to Escrow 910,000.00 12. Net Pymt. this Estimate 297,350.15