Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 15-209-10-08 04-235844 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 22% Location: Federal Project: 04-SM-101-16.3/17.1 NHP-Q101(237) CML-6204(113) Progress payment No. 012 Payment period ending: 07-20-15 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,147,880.51 0.00 2. a. Extra Work 732,360.56 0.00 b. Adustment Comp. -20,686.58 0.00 3. Materials on Hand 211,741.07 84,740.00 4. Earned Subject to Retention 13,071,295.56 84,740.00 5. Mobilization 3,610,000.00 0.00 6. Total Work Completed 16,469,554.49 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,681,295.56 84,740.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,740.00