Dept. of Trans. PROGRESS Serial No. Contract No. 02-291-13-13 04-237604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 15% 04-SCL-280-R2.8/R4.4 Federal Project: ACIM-280-1(101) Progress payment No. 03 Payment period ending: 10-20-02 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 298,645.00 174,099.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 71,503.39 15,953.47 4. Earned Subject to Retention 370,148.39 190,052.67 5. Mobilization 150,100.00 31,600.00 6. Total Work Completed 448,745.00 7. Deductions 8. a.Contract Retentions -29,182.80 -11,173.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 491,065.59 210,479.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 210,479.44