Dept. of Trans. 95% REDUCTION Serial No. Contract No. 05-050-08-02 04-239704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SCL-101-50.1/50.4 Federal Project: NONE Progress payment No. 10 Payment period ending: 02-20-05 O C JONES AND SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 559,363.51 720.00 2.a. Extra Work 28,410.82 19,592.00 b. Adjustment Comp. 20,956.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 608,730.60 20,312.00 5. Mobilization 48,160.00 0.00 6. Total Work Completed 656,890.60 7. Deductions 8. a.Contract Retentions -30,436.53 -1,015.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 15,589.89 15,589.89 9. Total pay to Contractor 642,043.96 34,886.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,886.29