Dept. of Trans. PROGRESS Serial No. Contract No. 03-232-12-38 04-243004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 19% 04-ALA-880-15.4/17.9 Federal Project: ACIM-880-1(50) Progress payment No. 10 Payment period ending: 08-20-03 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 02011 Total Estimate This Estimate 1. Contract Itms Without Mobil. 478,471.50 129,217.50 2.a. Extra Work 6,330.00 6,330.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 484,801.50 135,547.50 5. Mobilization 85,500.00 0.00 6. Total Work Completed 570,301.50 7. Deductions -2,072.40 0.00 8. a.Contract Retentions -24,240.08 -4,378.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 543,989.02 131,169.49 10. Reduction Amt to Escrow 11. Payment to Escrow 24,240.00 12. Net Pymt. this Estimate 131,169.49