Dept. of Trans. PROGRESS Serial No. Contract No. 03-293-12-13 04-243004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 23% 04-ALA-880-15.4/17.9 Federal Project: ACIM-880-1(50) Progress payment No. 12 Payment period ending: 10-20-03 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 02011 Total Estimate This Estimate 1. Contract Itms Without Mobil. 629,219.00 122,434.00 2.a. Extra Work 7,053.82 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 636,272.82 122,434.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 726,272.82 7. Deductions -2,072.40 0.00 8. a.Contract Retentions -31,813.64 -6,121.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 692,386.78 116,312.30 10. Reduction Amt to Escrow 11. Payment to Escrow 31,810.00 12. Net Pymt. this Estimate 116,312.30