Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-14-37 04-245414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 37% 04-SON-101-19.5/21.6 Federal Project: ACNH-Q101(107) CML-6204(59) Progress payment No. 15 Payment period ending: 05-20-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,799,494.93 1,731,873.00 2.a. Extra Work 623,690.98 11,889.12 b. Adjustment Comp. 260,457.11 0.00 3. Materials on Hand 1,232,135.29 -19,912.00 4. Earned Subject to Retention 25,915,778.31 1,723,850.12 5. Mobilization 6,171,261.75 0.00 6. Total Work Completed 30,854,904.77 7. Deductions -529.26 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,086,510.80 1,723,850.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,723,850.12