Dept. of Trans. PROGRESS Serial No. Contract No. 07-166-08-24 04-245414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 39% 04-SON-101-19.5/21.6 Federal Project: ACNH-Q101(107) CML-6204(59) Progress payment No. 16 Payment period ending: 06-20-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,565,962.88 1,766,467.95 2.a. Extra Work 626,447.00 2,756.02 b. Adjustment Comp. 260,457.11 0.00 3. Materials on Hand 1,305,745.24 73,609.95 4. Earned Subject to Retention 27,758,612.23 1,842,833.92 5. Mobilization 6,171,261.75 0.00 6. Total Work Completed 32,624,128.74 7. Deductions -529.26 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,929,344.72 1,842,833.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,842,833.92