Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-11-17 04-245414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 48% 04-SON-101-19.5/21.6 Federal Project: ACNH-Q101(107) CML-6204(59) Progress payment No. 19 Payment period ending: 09-20-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,423,968.94 3,837,854.91 2.a. Extra Work 742,391.53 38,947.80 b. Adjustment Comp. 342,582.99 0.00 3. Materials on Hand 801,986.50 -285,179.00 4. Earned Subject to Retention 35,310,929.96 3,591,623.71 5. Mobilization 6,171,261.75 0.00 6. Total Work Completed 40,680,205.21 7. Deductions -529.26 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,481,662.45 3,591,623.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,591,623.71