Dept. of Trans. PROGRESS Serial No. Contract No. 07-142-10-55 04-246804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 44% 04-SM-101-16.4/25.1 Federal Project: 04-SM-280-17.3/27.1 NH 04-SF-280-0.1/6.4 Progress payment No. 04 Payment period ending: 05-20-07 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 02284 Total Estimate This Estimate 1. Contract Itms Without Mobil. 522,996.40 220,313.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 522,996.40 220,313.40 5. Mobilization 237,500.00 50,000.00 6. Total Work Completed 760,496.40 7. Deductions -19,899.95 -4,189.46 8. a.Contract Retentions -40,819.54 -10,551.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 699,776.91 255,572.70 10. Reduction Amt to Escrow 11. Payment to Escrow 40,810.00 12. Net Pymt. this Estimate 255,572.70