Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-08-06 04-246934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 0% 04-SCL-101-0.0/ .0 Federal Project: 04-SCL-0-0.0/ .0 NONE 04-SCL-0-0.0/ .0 Progress payment No. 01 Payment period ending: 06-20-06 STEVENS CREEK QUARRY INC 12100 STEVENS CANYON ROAD CUPERTINO CA 95014 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 155,651.50 155,651.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 155,651.50 155,651.50 5. Mobilization 108,750.00 108,750.00 6. Total Work Completed 264,401.50 7. Deductions 8. a.Contract Retentions -15,565.15 -15,565.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 248,836.35 248,836.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,836.35