Dept. of Trans. PROGRESS Serial No. Contract No. 04-324-11-02 04-248104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 100% 04-ALA-880-11.4/12.4 Federal Project: ACIM-880-1(52) Progress payment No. 09 Payment period ending: 11-20-04 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,269,761.28 19,617.00 2.a. Extra Work 385,802.48 159,620.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,655,563.76 179,237.11 5. Mobilization 186,000.00 0.00 6. Total Work Completed 1,841,563.76 7. Deductions 8. a.Contract Retentions -82,778.19 -8,961.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,758,785.57 170,275.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 170,275.25