Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-09-06 04-249044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 80% 04-ALA-238-14.2/16.7 Federal Project: 04-ALA-880-18.3/20.7 STPL-6204(57) 04-ALA-580-R29.4/R31.4 Progress payment No. 36 Payment period ending: 07-20-09 FLATIRON WEST INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,711,238.06 1,488,635.01 2.a. Extra Work 4,973,541.10 96,640.55 b. Adjustment Comp. 2,767,868.40 43,073.31 3. Materials on Hand 137,568.03 -36,656.31 4. Earned Subject to Retention 86,590,215.59 1,591,692.56 5. Mobilization 8,540,000.00 0.00 6. Total Work Completed 94,992,647.56 7. Deductions -83,400.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 95,046,815.59 1,596,692.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,596,692.56