Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-09-11 04-2490A4 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 04-ALA-238-14.5/16.5 IM-X001(551) 04-ALA-880-20.3/20.8 Progress payment No. 043 Payment period ending: 04-20-15 J J NGUYEN INC 3172 SALEM DRIVE SAN JOSE, CA 95127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,162,896.50 3,375.00 2. a. Extra Work 58,725.93 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,221,622.43 3,375.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,311,622.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,311,622.43 3,375.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,375.00