Dept. of Trans. PROGRESS Serial No. Contract No. 01-236-10-17 04-250404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 78% 04-SCL-101-31.2/33.5 Federal Project: ACNH-P101(955) Progress payment No. 03 Payment period ending: 08-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01741 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,589,715.88 771,055.08 2.a. Extra Work b. Adjustment Comp. -10,000.00 -10,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,579,715.88 761,055.08 5. Mobilization 6. Total Work Completed 1,579,715.88 7. Deductions -13,195.56 -12,632.40 8. a.Contract Retentions -78,985.79 -38,052.75 b. Unsatisfactory Prog. 0.00 33,442.63 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,487,534.53 743,812.56 10. Reduction Amt to Escrow 11. Payment to Escrow 40,000.00 12. Net Pymt. this Estimate 743,812.56