Dept. of Trans. PROGRESS Serial No. Contract No. 01-294-20-01 04-250404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 04-SCL-101-31.2/33.5 Federal Project: ACNH-P101(955) Progress payment No. 05 Payment period ending: 10-19-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01741 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,857,329.83 24,196.87 2.a. Extra Work 28,682.29 2,457.07 b. Adjustment Comp. -13,849.30 -3,849.30 3. Materials on Hand 4. Earned Subject to Retention 1,872,162.82 22,804.64 5. Mobilization 6. Total Work Completed 1,872,162.82 7. Deductions -15,895.98 0.00 8. a.Contract Retentions -93,608.14 -1,140.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,762,658.70 21,664.41 10. Reduction Amt to Escrow 11. Payment to Escrow 93,600.00 12. Net Pymt. this Estimate 21,664.41